As extra authorities acquisition packages undertake an Agile growth methodology, there are extra alternatives for Agile to work together with and maybe cope with earned worth administration (EVM) ideas. EVM has been a mainstay throughout the U.S. authorities acquisition neighborhood for longer than Agile has, however each are firmly entrenched in coverage that mandates their use. Whereas not all EVM packages are Agile and never all Agile packages use EVM, it’s turning into extra widespread that authorities packages use each strategies. Professionals throughout the acquisition neighborhood are normally extra comfy with one methodology than they’re with the opposite, and a few even understand them to be at odds. This notion is maybe forgivable upon examination of the elemental assumptions for each practices. This weblog publish will focus on the interactions between Agile and EVM.
To establish potential disconnects and to assist acquirers achieve most profit from these methodologies, we focus on on this publish a few of the variations between Agile and EVM and discover concepts for tips on how to make them work effectively collectively. We summarize the principle supply of incompatibility, perceived or in any other case, as follows:
- EVM makes an attempt to baseline the venture administration triangle of value, schedule, and efficiency early in a program’s lifecycle. The aptitude evolution (efficiency) of the system being acquired is mapped over time (schedule) with the labor and supplies (value) wanted to carry out the event. These components are captured within the efficiency measurement baseline (PMB). This system’s earned worth administration system (EVMS) assesses the precise value and schedule to attain the acknowledged efficiency evolution towards the predicted value and schedule that’s baselined within the PMB. Basically, with this technique, the answer is fastened early and the EVMS assesses worth by how effectively this system progresses to that resolution based mostly on how a lot value and schedule it takes to attain it.
- Agile inverts this PM triangle as a result of it makes use of cadence-based planning as a substitute of the capability-based planning utilized by EVM. The iterative and glued timeboxes that Agile employs to develop the system being acquired welcome evolutionary adjustments within the system’s efficiency as a result of studying is anticipated over time. With Agile, value and schedule are comparatively fastened throughout the iterative timeboxes, and the answer that emerges is assessed for worth.

Determine 1: Conventional Undertaking-Administration Triangle vs. Inverted Agile Triangle
EVM and Agile each drastically affect how a program conducts operations and informs its choices. Agile, although, is extra involved with the method, and EVM is extra involved with measuring the efficiency of that course of, when it comes to value and schedule. These strategies may and will assist one another. But, anecdotal proof captured in SEI engagements with packages reveals that many packages are struggling to observe Agile growth processes and precisely measure their progress with EVM.
Acknowledging that each EVM and Agile methods are normally tailor-made to satisfy the wants of every program, we is not going to take a one-size-fits-all method on this publish to unravel this dilemma. (It is value acknowledging that Agile ideas additionally apply effectively to ongoing evolution of a deployed system, the place steady supply fashions are used. In these settings, constructs that derive from Kanban and eXtreme Programming might be extra outstanding than the acquainted constructs of Scrum. As effectively, in these settings, EVM will not be used, or could also be utilized very in a different way.) As a substitute, we’ll spotlight the place SEI workers members have noticed a few of the extra problematic interactions. The next will present some real-world concerns that acquisition professionals ought to pay attention to with Agile and EVM acquisition packages and tasks. Ideally, these concerns can be resolved early in a program’s lifecycle, however they are often encountered all through this system’s evolution.
Massive Design Up Entrance (BDUF) Versus Planning as Late as Potential
Conventional acquisition professionals are biased towards planning the way forward for this system with as a lot outlined granularity within the schedule as potential to assist the varied programs engineering technical opinions (SETRs). The SETRs perform as formal and complete opinions the place this system is meant to convey how effectively the design is known and justify the associated fee and schedule to develop. This method encourages a program to forecast a mature, long-term plan and supply the artifacts to assist and defend that plan, manifesting in a plan-driven, fixed-requirements method, sometimes called large design up entrance (BDUF). The EVMS measures progress towards that plan, and acquirers consider this system’s success based mostly on its adherence to the plan. This conventional method, which is sort of muscle reminiscence to many within the acquisition neighborhood, can discourage program agility all through the efficiency interval when new info, studying, or technological advances could recommend a greater however completely different path ahead.
Conversely, the Agile technique usually presumes that this system doesn’t know as a lot now as it’ll later, and never solely permits but in addition expects options to evolve over time with studying. Program pivots are made as long as evolutionary adjustments match throughout the comparatively fastened cost-and-schedule guiderails. Usually, Agile will use timeboxed planning that has comparatively brief home windows of time to study, develop, and consider the answer set. There’s minimal element planning past the present release-planning timebox, sometimes called the program increment/planning interval (PI) or the Agile cadence launch. Finally these two mindsets (conventional acquisition BDUF and Agile) will conflict early in this system, usually as the primary SETR approaches.
These two mindsets might be considered two ends of a planning continuum—large up-front (long-term) planning versus cadence-based short-term planning (typically known as rolling wave planning). A program ought to pay attention to the professionals and cons of every. The EVM mindset is usually related to a BDUF method, and it’ll seemingly be extra acquainted to the group’s professionals. However EVM is much less versatile in supporting the answer and necessities flexibility which are basic to Agile. Profitable packages discover a stability between such extremes, and managing progress requires long-term however less-defined high-level plans and short-term element planning captured within the EVMS. It’s greatest that this system supervisor, EVM, and engineering communities focus on this continuum early and be sure that they’re synchronized to stop confusion later.
As is normally the case, the optimum method lies someplace in between, and it’s situational. Generally, the bigger the viewers or the upper up within the organizational hierarchy that the choice straight impacts, the earlier the choice and planning needs to be carried out. Usually this case implies that enterprise-wide planning occurs earlier than portfolio planning, and portfolio planning occurs earlier than crew planning. This method is especially related with architectural planning choices. For example, in programs of programs, the architectural plan and imaginative and prescient have to be sufficiently outlined up entrance to allow groups to construct suitable work. Issues like communication protocols, working programs, and timing, which have an effect on the whole enterprise, are greatest decided up entrance. However architectural choices that have an effect on solely a single crew needs to be deferred till later to use potential tradeoffs earlier than being documented and applied.

Determine 2: Hierarchy of Planning Ranges
Assessing Feasibility
Each EVM and Agile growth place vital emphasis on assessing the feasibility of a program; nevertheless, there are vital variations of their approaches.
For packages that may use EVM, there’s a requirement that an built-in baseline overview (IBR) be carried out by which each work and organizational buildings are examined within the context of schedule, funds, and different sources, in addition to any identified dangers. The primary functions of the IBR are to establish extra threat and assess whether or not the baseline defines a program that may be achieved. The EVM crew performs a big position in assessing the feasibility of this system. In essence, the IBR is a forward-looking, multi-factor (e.g., value, schedule, efficiency, threat) method to assessing feasibility based mostly on the plans developed for this system.
In distinction, Agile packages, significantly these following the Lean Startup mannequin, concentrate on the event of a minimal viable product (MVP), which is a growth of software program to verify or refute the speculation that this system (or some a part of it) is possible. It is an engineering downside, based mostly on schedule and complexity, to find out when an MVP can and needs to be produced. For the reason that MVP have to be constructed first, feasibility is assessed in a backward-looking method to find out whether or not the speculation was sustained.
In massive, complicated packages, an IBR could happen lengthy earlier than an MVP might be developed, significantly when the speculation to be examined is of a fancy nature. Furthermore, the IBR considers a broad vary of things whereas the everyday MVP is restricted to answering a smaller set of questions. The MVP, nevertheless, is a concrete demonstration, based mostly on executing code, whereas the IBR is invariably based mostly on projections into the long run.
The 2 approaches are suitable with one another. For giant packages that may use each Agile strategies and EVM, it’s seemingly that an IBR might be carried out as standard, although it needs to be thought of that part of the IBR would possibly embody an illustration of an MVP (if it may be developed in time). Whatever the presence of an MVP, the next questions needs to be answered no later than the IBR:
- How will the EVM and Agile buildings be aligned in order that the EVM coding buildings [such as the work-breakdown structure (WBS) and organizational breakdown structure (OBS)] are mirrored within the software lifecycle administration device’s hierarchy?
- How will the Agile roadmap be synchronized with EVM artifacts such because the built-in grasp schedule (IMS)?
- How are the Agile backlog(s), priorities, and commitments built-in with the approved scope?
- How will the baseline schedule be aligned with the Agile cadence-based timeboxes?
- What mechanisms might be used to replicate Agile studying within the baseline schedule?
- How will rework be dealt with?

Determine 3: EVM Plan Vs. Agile Product Viability
How Far Down into the Hierarchy of Agile Work Does the EVMS Observe?
Traditionally, packages have adopted the BDUF technique; not just for the system to be constructed, but in addition for all of the related administration processes. The system isn’t the one factor designed up entrance; so are all organizational and administration buildings. These organizational designs sometimes observe the organizational assemble and sometimes usually are not seen in Agile developments, although latest work in crew topologies suggests mechanisms for organizing the groups in response to the specified construction of the system. For each the system and the organizational construction, although, there’s a rigidity between basically fastened buildings in a conventional growth and fluid buildings in an Agile growth.
An Agile program’s growth work is damaged down into hierarchical classes based mostly on their ontology. Usually, the best ranges of labor, usually known as epics, would be the overarching capabilities or necessities that may take years to finish. This system will then break down that increased degree work into smaller, extra outlined items that match throughout the completely different timeboxed cadence releases and iterations. A generally prescribed hierarchy can be to have epics on the prime, then options, and eventually tales on the lowest degree.
Options are normally outlined as element deliberate work that matches inside a program’s Agile cadence launch or PI and supplies demonstrable worth. Tales are sometimes items of labor that may be completed by an Agile crew that match inside an iteration timebox, normally 1 to 4 weeks. Nevertheless, this nominal hierarchy of epicsàfeaturesàstories is usually not practiced. Many packages have greater than three ranges of hierarchy and use completely different terminology and definitions for causes distinctive to them. Usually the terminology will evolve over a program’s growth lifetime to accommodate altering enterprise and engineering practices.

Determine 4: Nominal Agile Hierarchy and Length to Full
No matter terminology or what number of ranges, all Agile packages may have a breakdown of labor that the EVMS will inevitably need to measure. Naturally, some might imagine that the EVMS ought to observe the bottom degree of labor since it’s normally essentially the most outlined and element deliberate. Nevertheless, this method will seemingly be administratively burdensome and pointless as a result of the bottom degree of labor is just too detailed for the bigger growth context. The characteristic degree of labor (utilizing the above paragraph’s nominal hierarchy and terminology) will virtually definitely present ample measurable worth to the general program necessities with out having so as to add so many detail-planned work packages into the PMB.
The most effective degree of monitoring is to go no decrease than is critical, however low sufficient to realize the attitude wanted for administration to make the best choices. A program must decide what works for them early and be sure that it may be utilized uniformly. In any other case, disconnects between the enterprise and growth crew will happen.
Resolving the Rigidity Between Relative and Absolute Estimation
Estimation is utilized by each EVM and Agile growth however with completely different targets in thoughts and, consequently, completely different approaches. In follow neither method assumes excellent estimates. Estimation in EVM is meant to supply administration with an evaluation of how lengthy it’ll take and the way a lot it’ll value to construct a required artifact. Consequently, these estimates are normally given in models of time and prices related to parts to be constructed. Earned worth is then assessed by comparability of precise time and prices together with reported progress to the estimates.
In distinction, in Agile growth, estimation is used virtually solely for assessing the feasibility of near-term (and team-specific) targets. Nevertheless, these estimates are sometimes divorced from any models. The crew performing the estimation identifies the smallest work merchandise then assesses all different work gadgets relative to the smallest work merchandise; no models are implied by the estimate. Furthermore, these estimates are sometimes created on the time work is about to start and never at some interval upfront, as is critical for conventional EVM.
For each EVM and Agile, the estimates are based mostly on historic efficiency. Within the case of EVM the historical past comes from previous packages, whereas in Agile the historical past is from latest timeboxes. In concept, the Agile estimates needs to be extra correct as a result of they’re based mostly on up-to-date info, however these estimates might be flawed, significantly when there’s administration stress to hit schedule targets. A ultimate consideration is that the everyday EVM estimate of effort is mostly created in a top-down trend constrained by the ultimate negotiated contract, whereas Agile proponents suggest that the groups develop their estimates with a bottom-up method.
Any Agile growth that can be being tracked with EVM should cope with the difficulty of tips on how to convert unitless measures to unit-based measures. There are a number of methods this is likely to be completed:
- Settlement that every level equates to some variety of hours of growth work–This settlement is usually completed by estimating in “preferrred days” as described effectively by Mike Cohn in his ebook Agile Estimating and Planning. Though this method is practiced regularly, there are downsides to this method as a result of it encourages the crew to suppose in absolute moderately than relative estimates. The human mind is nice at relative estimation. For example, take into account the completely different cup sizes on show on the espresso store; with out realizing absolutely the portions, we will nonetheless shortly determine which dimension we would like. One other draw back is that preferrred days imply that the crew should estimate not solely activity dimension but in addition activity period, whereas relative estimation is targeted solely on dimension. Chapter 8 of Cohn’s ebook is a superb useful resource for extra element on this matter.
- Utilizing a variable mapping of factors to hours—This mapping could possibly be achieved by summing up all of the factors related to a bit of labor after which dividing absolutely the estimate produced for EVM functions by the factors to get the mapping for this piece of the work. This might require that the Agile crew decide to the preliminary estimate of all of the work, which can discourage studying as the event progresses. Additional, it will be meaningless to match story-point velocities inside a crew from one piece of labor to the subsequent since it will be unlikely that the ratio of hours to factors can be the identical on any two items of labor.
- Merely ignoring the variations between story factors and hours (or preferrred days)—The previous recommendations level out difficulties with reconciling story factors and hours. The query would then come up as to the worth of utilizing two completely different estimation methods that, significantly for calculation of progress (% full) can be unlikely to provide the identical solutions. Coverage paperwork sometimes outline tips on how to use story factors to compute % full of a characteristic however give no steering with respect to calculation of prices that might be higher centered on precise hours vs. deliberate hours for accomplished work. The problem is that, for good causes of consistency, EVM requires that value and schedule efficiency indicators be based mostly on the identical information and models. Subsequently, it could make sense to permit Agile groups and EVM system customers to make use of their very own estimates and never attempt to reconcile them outdoors of the context for which they have been supposed.
Phrases Matter—Agree Early
Vocabularies are essential and foster a typical understanding. A shared vocabulary is especially essential in Agile–EVM discussions for the reason that communities (builders and program administration) are sometimes new to or not very acquainted with one another’s phrases. If folks don’t take time to develop a typical understanding of phrases, they are going to consider that they’ve agreements when, actually, they don’t due to completely different interpretations of the phrases used.
Agile and EVM each deliver an intensive listing of not-so-common terminology to an already vocabulary-dense world of DoD acquisitions. It’s seemingly that two events in the identical program have nuanced interpretations of the identical phrase, even after they’ve been on this system for some time. Worse, SEI Agile and EVM practitioners have noticed that the Agile hierarchy phrases and the definitions of every degree is usually a supply of confusion and disconnect. These issues can occur as a result of many packages will evolve their Agile hierarchy by including or eradicating ranges, which is able to drive updates to their definitions. The Agile hierarchy kinds the structure by which the EVMS will consider this system’s growth progress (see How Far Down into the Hierarchy of Agile Work Does the EVMS Observe?, above). Subsequently, Agile terminology adjustments are analogous to engineering adjustments, and the operational definition of key phrases could should be managed in a equally rigorous trend.
A phrase of warning: When widespread Agile phrases, corresponding to characteristic or epic, are used in a different way, there’s a threat of bewilderment with outdoors entities as effectively since these phrases are sometimes utilized by different packages.
What’s the Proper Quantity of Administrative Evaluation When Doing Baseline Change Requests (BCRs)?
When an Agile program plans its work for the subsequent cadence launch or PI, work might be decomposed from the bigger gadgets within the hierarchy, and element planning will happen with essentially the most up-to-date info. Normally that is finished collectively throughout the enterprise with subject-matter specialists and stakeholders included for buy-in. The agreed-upon deliberate work then must be captured within the EVMS, which would require baseline change requests (BCRs).
With a conventional plan-driven method [see Big Design Up Front (BDUF) Versus Planning as Late as Possible, above], BCRs are sometimes considered to be fixes to errors within the plan—they’re deviations from the in any other case long-term plan that isn’t supposed to vary underneath the standard acquisition paradigm. Due to this, the everyday BCR course of requires oversight by stakeholders related to the BCR, typically by a BCR board, who overview to find out if the change might be made to the PMB. Usually, the specialists which are required to overview and approve the BCR have been current within the PI planning that generated the BCR. Subsequently, this BCR oversight by a board could also be duplicative and pointless, particularly if the EVM material specialists, just like the management account managers (CAMs) and planners, are additionally part of the discharge planning to make sure that EVM guidelines aren’t breached and sudden schedule perturbations don’t happen.
Applications could need to have two completely different BCR approval processes:
- A streamlined course of for the planning adjustments which are recognized within the cadence-release/PI planning occasions when all stakeholders are current, and
- A conventional, extra thorough overview course of (if wanted) for adjustments that happen outdoors of the release-planning occasions.
Whatever the approval course of that’s used, it’s additionally essential to leverage software lifecycle administration instruments and real-time info flows to contain stakeholders in a well timed and environment friendly method, and to make sure that the suitable persons are concerned to approve a BCR.
Assessing Progress
EVM’s worth is derived from its use of precise project-performance information to measure progress. This information is then used to find out the worth of the work accomplished. The simplest and most typical method is bodily % full. Whereas it’s easy and simple to grasp as a result of it’s based mostly on tangible proof of labor completion, it could not take into account fixed adjustments to the scope of the venture, could possibly be topic to interpretation, and will not present a constant view of progress throughout completely different groups.
Inside the Agile philosophy, worth is achieved solely with working software program. Within the strictest implementation, there can be solely two choices: 0 % or 100% full. Likewise, EVM steering means that if work packages might be accomplished inside one reporting cycle, a 0/100 measure of completeness can be acceptable.
Giant programs of programs usually require involvement with organizations outdoors the management of the software program builders, corresponding to formal take a look at organizations, certification authorities, platform integration, and many others. This method doesn’t precisely signify accomplished work and makes accounting for rework troublesome.
On this case, the usage of 0/X/…/Z/100 methodology makes extra sense. Every stage or state is represented with a worth of completion agreed to upfront. Applications must decide what the middleman values needs to be. These values function indicators of stage or state completions versus a precise share full.
For instance, if the system required exterior testing and formal certification, a 0/30/75/100 valuation could also be deemed acceptable. The work bundle can be decided to be 30 % full when it was prepared for the exterior testing. It might then be assessed at 75 % after testing and any required rework was accomplished. Lastly, after certification (and any rework) was full, it will be closed out at 100% full.
Setting Up an EVM and Agile Program for Success: The Twain Shall Meet
All these concerns are simply that—concerns. Every program has nuances that may decide what the most effective path ahead is for his or her state of affairs. It’s thrilling to know that there is no such thing as a one precise method to do that, however as a substitute there are seemingly limitless methods to arrange an EVM and Agile program for achievement. The setup could even be extra of an artwork than a science.
Our expertise reveals that practitioners of EVM and Agile will seemingly encounter all of the tradeoffs detailed on this publish (and possibly extra that weren’t listed). Despite the fact that there’s not one proper method to treatment these, there’s proof that early engagement between EVM and Agile stakeholders can cut back potential for each disciplines to develop into burdensome and as a substitute work collectively to supply priceless perception in managing the outcomes of effort. As with most significant issues in life, groups must adapt by way of the interval of efficiency, so it’s essential to undertake a studying mindset and arrange the Agile and EVM framework to permit for evolution.
We hope that this weblog publish highlights a few of the essential commerce areas early for the readers in order that practitioners might be ready to consider them earlier than they current severe issues. All of the completely different concerns enumerated on this publish underscore the should be aware when using Agile and EVM; it’s not simply enterprise as standard. It’s essential to recollect the intent of Agile and EVM and leverage essentially the most helpful parts of every whereas not utilizing the parts that take away from program execution and monitoring. When finished appropriately, practitioners will benefit from the deserves of each practices.